I had enable the schedule backup attempts to re-run the failed backup jobs over a specified time period.

Is there a setting to specific the period to run on each individual job? eg. job A to re-run after 2 hours, job B to re-run after 5 hours, job C not to re-run?

Thanks.
3 REPLIES 3

Yasuhisa_Ishika
Level 6
Partner Accredited Certified
Job retry delay affects all policies with same delay.
The only way to get it possible is to omit NetBackup schedule and run(re-run) all manually.

Jess_Lee
Level 4
Thanks for the reply. I'd read through job retry delay and also schedule backup attempts on host properties. Still not quite clear on the differences between both of them.

In my senario, I should modify job retry delay or schedule backup attempts? Thank you.

Yasuhisa_Ishika
Level 6
Partner Accredited Certified
Both affect all policies.
schedule backup attempts defines max number of attempts and time range.