When Re-Schedule Job Changed , Date will miss

Prasert_Binsale
Not applicable
Partner Accredited Certified
Hi,

I am working with BSR V6.5 have experience problem about when I change schedule job then Date will miss changed error!!!

Now I set Location in Regional as Thai, Standards and Formats as English

such as The first job is setting running on 5/10/2549 after that modify time in that job then date become 5/10/3092 automatically.

If you have this experience please advise me.

Thanks so much.
1 REPLY 1

techno_nerd
Level 4
Prasert,

Are you saying if you change your schedule, the date will change to May 10, 3092 automatically? Or when you modify the date, it misses image create jobs?