My full backup is scheduled on weekly basis i.e., every week sunday and incrementals are running every day. My query is will both full and incremental backup run on sunday, if so I  want to exclude incremental on sundays. Is it possible to do. Will it affect backup cycle?

Thanks in advance.

 

1 ACCEPTED SOLUTION

Accepted Solutions

pkh
Moderator
Moderator
   VIP    Certified
You should be the one to close the discussion by clicking on the Mark as solution link under my answer

View solution in original post

3 REPLIES 3

pkh
Moderator
Moderator
   VIP    Certified
If both your full and incremental backups start at EXACTLY the same time then the full backup will supersede the incremental backup because it has a less frequent schedule

geeksbkup
Level 3

Hi,

  Thanks for clarifying the issue. My full and incremental backup starts at 6.00AM every week(full) everyday(inc). Kindly mark the thread as 'SOLVED'.

pkh
Moderator
Moderator
   VIP    Certified
You should be the one to close the discussion by clicking on the Mark as solution link under my answer