I run the EVSVR utility in arc server to idetify how many DVS files are missing. I found the following result.

Saveset records: 4958742

2012-12-15 00:29:32 

2012-12-15 00:29:32  Stop Requested

2012-12-15 00:29:32 

2012-12-15 00:29:34 

2012-12-15 00:29:34            Savesets processed:              3577864

2012-12-15 00:29:34            Savesets with missing SIS Parts: 0

2012-12-15 00:29:34 

2012-12-15 00:29:34            Savesets without SIS Parts:      2070131 (57.9%)

2012-12-15 00:29:34            Savesets with SIS Parts:         1507733 (42.1%)

2012-12-15 00:29:34 

Here the saveset records are not matching with saveset processed? DO  you have any idea why it is happening like this?

 

1 ACCEPTED SOLUTION

Accepted Solutions

JesusWept3
Level 6
Partner Accredited Certified
Are you absolutely sure?? The fact it says stop requested means literally what it says, that something or someone requested it to stop The log should end like this 2011-01-27 14:10:38 Processing rate: 399694 Items/hour 2011-01-27 14:10:38 Elapsed time: 0 days, 2 hours, 47 minutes, 9 seconds 2011-01-27 14:10:38 2011-01-27 14:10:38 Operation completed 2011-01-27 14:10:38 2011-01-27 14:10:38 Log file closed
https://www.linkedin.com/in/alex-allen-turl-07370146

View solution in original post

6 REPLIES 6

JesusWept3
Level 6
Partner Accredited Certified
Well I could be wrong but it was told to stop before it finished?
https://www.linkedin.com/in/alex-allen-turl-07370146

TonySterling
Moderator
Moderator
Partner    VIP    Accredited Certified

I agree with JW3, it appears that the stop command was issued before it had a chance to complete.

chinmayams
Level 2

No . It was not asked any thing to stop inbetween. but  when the utility completed i checked the log and it was showing as stoped.

JesusWept3
Level 6
Partner Accredited Certified
Are you absolutely sure?? The fact it says stop requested means literally what it says, that something or someone requested it to stop The log should end like this 2011-01-27 14:10:38 Processing rate: 399694 Items/hour 2011-01-27 14:10:38 Elapsed time: 0 days, 2 hours, 47 minutes, 9 seconds 2011-01-27 14:10:38 2011-01-27 14:10:38 Operation completed 2011-01-27 14:10:38 2011-01-27 14:10:38 Log file closed
https://www.linkedin.com/in/alex-allen-turl-07370146

chinmayams
Level 2

my company believes we have lost DVS and DVSSP files.  Using the EVSVR tool what configuration is best to use that will tell me if the file is missing with the quickest response time?  I have a global configuration but I only want to validate a single Vault store group.

AndrewB
Moderator
Moderator
Partner    VIP    Accredited

you can select whatever vault store you want to check in EVSVR, you can even drill down to a lower level but i would strongly recommend opening a support case if you believe you have data loss and need to analyze with EVSVR.