Hi All,

Got a question about the Disk Staging Schedule. I've set it up for our Disk Staging STU with the final destination to an LTO library with one LTO2 drive. I've done the setup through the GUI.

What I see is that mostly three jobs get started and mostly two of them fail with server resources busy. I can imagine that, because I only have a single drive. But when I look a the schedule, it's not possible for me to tell how many jobs get scheduled (in the GUI).
I also noticed that sometimes 4 jobs get scheduled for the duplication.

How can I reduce the number of jobs that get started? Or if that is not possible how can I manage when the jobs get started, e.g. how can I manipulate it, so that the biggest image is the last one in line, instead of now being mostly the first in line?

Any help is appreciated.

Regards,

Richard.
1 REPLY 1

Richard_van_Den
Level 4
Solved by using MAX_STAGING_JOBS