04-05-2012 07:51 AM
Hello,
I have a problem with exchange 2010 backup.
During this backup, I have the message "05/04/2012 16:00:33 - Info bpbrm(pid=9472) from client dag-1: TRV - Granular processing failed! "
The NFS process working good between media server (MSDP NBU 7.1.0.3) and exchange client (NBU7.1.0.3). I have tested with nbfsd command in media server and nbfs in exchange client.
Detailed Status
05/04/2012 15:50:28 - Info bpbrm(pid=9472) SREXMBX01 is the host to backup data from
05/04/2012 15:50:28 - Info bpbrm(pid=9472) reading file list from client
05/04/2012 15:50:32 - Info bpbrm(pid=9472) starting bpbkar32 on client
05/04/2012 15:50:45 - Info bpbkar32(pid=11732) Backup started
05/04/2012 15:50:45 - Info bptm(pid=14140) start
05/04/2012 15:50:45 - Info bptm(pid=14140) using 262144 data buffer size
05/04/2012 15:50:45 - Info bptm(pid=14140) setting receive network buffer to 1049600 bytes
05/04/2012 15:50:45 - Info bptm(pid=14140) using 30 data buffers
05/04/2012 15:50:47 - Info bpbkar32(pid=11732) INF - waiting for mount mutex
05/04/2012 15:50:47 - Info bpbrm(pid=9472) from client dag-1: TRV - NFS timeout value (10) is lower than recommended for NetBackup GRT.
05/04/2012 15:50:47 - Info bptm(pid=14140) start backup
05/04/2012 15:50:50 - Info bptm(pid=14140) backup child process is pid 3336.6888
05/04/2012 15:50:51 - Info bptm(pid=3336) start
05/04/2012 15:50:52 - Info nbjm(pid=5308) starting backup job (jobid=180085) for client SREXMBX01, policy Test_Antemeta, schedule test-AA
05/04/2012 15:50:52 - estimated 26685236 Kbytes needed
05/04/2012 15:50:52 - Info nbjm(pid=5308) started backup job for client SREXMBX01, policy Test_Antemeta, schedule test-AA on storage unit SU_IRM
05/04/2012 15:50:53 - started process bpbrm (9472)
05/04/2012 15:51:01 - connecting
05/04/2012 15:51:04 - connected; connect time: 00:00:03
05/04/2012 15:51:22 - begin writing
05/04/2012 16:00:28 - Info bpbrm(pid=9472) DB_BACKUP_STATUS is 0
05/04/2012 16:00:31 - Info bpbrm(pid=9472) from client dag-1: TRV - Starting granular backup processing for (/Microsoft Exchange Database Availability Groups/dag-1.ch-sainte-anne.fr\Microsoft Information Store:\DB-10000-02\). This may take a while...
05/04/2012 16:00:33 - Info bpbrm(pid=9472) from client dag-1: TRV - Granular processing failed!
05/04/2012 16:00:33 - Info bptm(pid=14140) waited for full buffer 4536 times, delayed 28223 times
05/04/2012 16:00:33 - Error bpbrm(pid=9472) from client dag-1: ERR - Error encountered while attempting to get additional files for Microsoft Information Store:\DB-10000-02\Logs_1333633802\
05/04/2012 16:00:33 - Error bpbrm(pid=9472) from client dag-1: ERR - Exchange granular restore from this image may not work.
05/04/2012 16:00:43 - Info bptm(pid=14140) EXITING with status 0 <----------
05/04/2012 16:00:43 - Info srnbkms03(pid=14140) StorageServer=PureDisk:srnbkms03; Report=PDDO Stats for (srnbkms03): scanned: 22238731 KB, stream rate: 158.93 MB/sec, CR sent: 14276 KB, dedup: 99.9%, cache hits: 173523 (99.9%)
05/04/2012 16:00:43 - Info bpbrm(pid=9472) validating image for client dag-1
05/04/2012 16:01:18 - end writing; write time: 00:09:56
the requested operation was partially successful(1)
Thanks for your help.
Sebastien
Solved! Go to Solution.
04-05-2012 08:56 AM
Check that you have no issues with your exchange logs and that all replication etc. is up to date and working - that is normallyt what stops it - assuming it has ever worked?
04-05-2012 08:56 AM
Check that you have no issues with your exchange logs and that all replication etc. is up to date and working - that is normallyt what stops it - assuming it has ever worked?