07-29-2015 04:51 AM
I got a request to configure weekly backup and monthly backups for one client.
Where Weekly should be - Every Saturday 6:00PM & Monthly last Saturday of the month 6:00PM. And the Weekly backup shouldnt run on last saturday as monthly schedule.
So I created
For Weekly
New Scheulde --> Calender --> Calender Schedule --> Recurring Week Days & selected 1st,2nd & 3rd Saturday.
For Monthly
New Scheulde --> Calender --> Calender Schedule --> Recurring Week Days & selected Last Saturday.
Here the problem is some month has 5 saturdays, In that month if I schedule like above 4th Saturday Backup is missing. Considering that point and if I add 4th Saturday in weekly schedule for the month which as 4 saturday's on the 4th saturday both Weekly and monthly is running. How to over come from this?
Solved! Go to Solution.
07-29-2015 05:07 AM
Just add the 4th week to the weekly schedule. Then, NetBackup will run the monthly full schedule in a 4 week month, as it knows that this backup has not run for the longest period. It will work :) Just make sure that the 'run window' on each schedule covers the same time period.
.
FYI - Whilst your question is related to calendar based scheduling, if you did want to know more about frequency based scheduling, see Marianne's article here:
https://www-secure.symantec.com/connect/articles/netbackup-frequency-based-scheduling
...which also links to a copy, which Marianne also prepared, of an article by Dave Chappa.
07-29-2015 05:07 AM
Just add the 4th week to the weekly schedule. Then, NetBackup will run the monthly full schedule in a 4 week month, as it knows that this backup has not run for the longest period. It will work :) Just make sure that the 'run window' on each schedule covers the same time period.
.
FYI - Whilst your question is related to calendar based scheduling, if you did want to know more about frequency based scheduling, see Marianne's article here:
https://www-secure.symantec.com/connect/articles/netbackup-frequency-based-scheduling
...which also links to a copy, which Marianne also prepared, of an article by Dave Chappa.
07-29-2015 06:42 AM
Cool.. That looks it will be useful.
Read the below and tell me what happens.
1) Daily schedule with frequency option as 1 day at 8:00PM
2) Weekly Schedule created with calendar option at Every Friday 8:00PM.
So what happens to the daily job on Friday ?
07-29-2015 06:50 AM
On Fri, the wekely schedule should run, as this will have not run for the longest time, whereas the daily has run every previous day.
07-29-2015 06:53 AM
I got my answer from the Marianne prepared, of an article by Dave Chappa.
That was really awesome explanation and am clear now.