We have a Sony TSL-SA500C AIT3 Autoloader. It's identified by BE 9.1 as a SPECTRA. It is set to append, but one job takes 1.5 tapes. The following day's job will not use remaining capacity on the second, partially used tape. So we end up wasting tape. Can someone provide me with step-by-step instructions to get BE to use the entire capacity of each tape?

Thanks.
3 REPLIES 3

Ken_Putnam
Level 6
How are your jobs defined?

Overwrite? or Append? or Append, else overwrite?

If they are defined as Overwrite, then this is to be expected

if they are defined as Append. else overwrite, they should continue where the previous job left off, if they media set they use is the same

Mani_2
Level 6
Hello,

Kindly refer the following Technote and set the appropriate Media Set properties for Append Protection and Overwrite Protection.



http://seer.support.veritas.com/docs/237374.htm



Related Documents
===============



http://seer.support.veritas.com/docs/192265.htm




http://seer.support.veritas.com/docs/262055.htm



Hope this helps.

Abhinav_Bindroo
Level 6