Is there any way I can schedule restore jobs in Puredisk ?
I have been looking but can't see how it can be done...
Any help would be greatly appreciated!
Solved! Go to Solution.
11-26-2008 04:14 AM
PureDisk does not have the ability to schedule restores. You could use the PD-VFS (cifs) view of a dataselection to expose the files on the Content Router to a agent on which you could then run a script to do the restore.
hope that helps
Philip.
11-26-2008 04:14 AM
PureDisk does not have the ability to schedule restores. You could use the PD-VFS (cifs) view of a dataselection to expose the files on the Content Router to a agent on which you could then run a script to do the restore.
hope that helps
Philip.