I have a task scheduled for 5am every day. I am getting log entries like this:
"An automatic recovery point was not created because an earlier recovery point from the same job was still in progress"
There isn't any instance of this job in progress, and actually the recovery point is created on the external drive.
The log sequence is:
Info 6C8F1F65: The drive-based backup job, Drive Backup of SYS (C:\), Data (D:\), has been started automatically.
Details:
Source: Backup Exec System Recovery
---
Info 6C8F17E7: An automatic recovery point was not created because an earlier recovery point from the same job was still in progress.
Details: Operation aborted
---
Info 6C8F1F7E: A scheduled incremental recovery point of drive D:\ was created successfully.
Details:
Source: Backup Exec System Recovery
---
Info 6C8F1F7E: A scheduled incremental recovery point of drive C:\ was created successfully.
Details:
Source: Backup Exec System Recovery
This started happening after I manually cancelled a job a couple of days ago. It looks like there is an "invisible" job somewhere, not listed in the UI...
Any ideas?