07-09-2012 12:43 PM
Back in BE 2010, I was able to schedule jobs using a caledar like week/day feature which let's me select which days of month I want the job to run.
But How do I do the same on BE 2012?
For example: I have a weekly job that I want to run on every 2nd,3rd,4th saturday of each month. (How to do this without creating 3 separate jobs?)
Solved! Go to Solution.
07-10-2012 04:02 AM
@capriguy84 - as you mentioned, separate jobs will have to be created in BE 2012. We have received feedback about inability to select multiple week days in a monthly schedule, which could be done in BE 2010 and the same is under discussion.
Thanks,
Mandar
07-09-2012 12:49 PM
Go to Backup and Restore tab
right click on the server name - Edit Backups
Select the job - Ok
In Backup Properties - select Edit ont he right (beside Add Stage)
under 'Schedule section' - expand the "Recurrence" section to set the desidered Schedule
07-10-2012 04:02 AM
@capriguy84 - as you mentioned, separate jobs will have to be created in BE 2012. We have received feedback about inability to select multiple week days in a monthly schedule, which could be done in BE 2010 and the same is under discussion.
Thanks,
Mandar